132 kV SF6 Circuit Breakers at Dhalkebar Substation and Modi Khola Hydropower Station
Supply, delivery, installation, testing and commissioning of 132 kV outdoor SF6 circuit breakers for NEA at Dhalkebar Substation and Modi Khola Hydropower Station.
Project Overview
Overview
Mahavir Shree International Pvt. Ltd. has supplied, installed, tested and commissioned 132 kV outdoor SF6 circuit breakers for the Nepal Electricity Authority (NEA) under two contracts.
For NEA's Hetauda Grid Division, under contract HGD/2072/073-ES-T.No.-01, MSI supplied and commissioned a 132 kV, 1,250 A outdoor SF6 circuit breaker with spares at Dhalkebar Substation. For Modi Khola Hydropower Station, under contract 2073/74 MKHPS-ES-T1, MSI supplied and commissioned a 132 kV outdoor SF6 circuit breaker.
Scope & Deliverables
- 132 kV, 1,250 A outdoor SF6 circuit breaker with spare parts, Dhalkebar Substation
- 132 kV outdoor SF6 circuit breaker, Modi Khola Hydropower Station
- Installation, testing and commissioning
Outcome
NEA certified the Dhalkebar breaker as completed on 13 November 2016, and issued a final acceptance certificate for the Modi Khola breaker in November 2021, stating that the entire work was completed successfully.