New Khimti Substation Augmentation: Integrated Plant Procurement and Project Execution
Design, Supply, Construction/Installation, Testing and Commissioning of(Extension of 220 kV GIS at New Khimti S/S, Extension of 132kV AIS at New Khimti S/S, Construction of 33kV Indoor Vacuum System, Construction of 11kV Indoor Vacuum System) 220/132/33/11KV
Project Overview
The Procurement of Plant for New Khimti Substation Augmentation project was undertaken for Nepal Electricity Authority (NEA), Khimti Substation. The project covers an integrated scope of design, supply, construction/installation, testing, and commissioning required for the augmentation works at the New Khimti Substation.
The project comprises the following major components:
- Extension of 220 kV GIS at New Khimti Substation.
- Extension of 132 kV AIS at New Khimti Substation.
- Extension of New 220/132kV , 4 x 66.66MVA Single phase Auto Transformer
- Extension of New 132/33kV , 2 x 30MVA Three phase Power Transformer
- Extension of New 33/11kV , 6/8 MVA Three phase Power Transformer
- Construction of 33 kV Indoor Vacuum Switchgear System.
- Construction of 11 kV Indoor Vacuum Switchgear System.
- 132kV, 1200 sq.mm XLPE cable for the transformer Bay.
- 33kV & 11kV XLPE Cable for Indoor Switchgear.
- Fire Protection System for all Building and transformers
- Integration and augmentation of the 220/132/33/11 kV electrical system, including associated equipment, protection, control, and auxiliary systems.
The project commenced on 10 March 2020 and is scheduled for completion on 6 July 2024 under Contract ID No. ICB No. RGK-75/76-02. Its multi-stage scope requires close coordination between engineering, plant supply, site construction and installation, testing, and commissioning activities to maintain continuity between each phase of implementation.
MSI is responsible for coordinating the specified project activities from design through commissioning. The execution approach brings together technical planning, procurement, site implementation, system verification, and commissioning within a structured framework to support completion of the substation augmentation in accordance with the defined project requirements.
Objectives
The project was designed to achieve the following goals:
- To complete the design requirements for the New Khimti Substation Augmentation
- To procure and supply the plant required under the project scope
- To carry out the required construction and installation works for the substation augmentation
- To maintain coordination between design, plant supply, construction, and installation activities
- To test the installed plant and associated works prior to commissioning
- To complete commissioning in accordance with the defined project requirements
Key Deliverables
The following systems, instruments, and tools were supplied, installed, and commissioned as part of the project:
Design and Technical Coordination
- Design activities for the New Khimti Substation Augmentation
- Coordination of design requirements with plant supply and site implementation activities
Plant Supply
- Procurement and supply of plant required under the project contract
- Coordination of plant supply with the requirements of the augmentation works
Construction and Installation
- Construction activities associated with the New Khimti Substation Augmentation
- Installation of the supplied plant in accordance with the project requirements
- Coordination between construction and installation activities during site execution
Testing and Commissioning
- Testing of the installed plant and associated works
- Verification of completed installation works prior to commissioning
- Commissioning of the completed augmentation works in accordance with the project requirements
Challenges
The project involved several technical, execution, and coordination challenges associated with implementing a substation augmentation through an integrated project scope:
- Coordinating design, plant supply, construction/installation, testing, and commissioning as interconnected stages of the same project
- Managing the interfaces between engineering requirements, supplied plant, and site installation activities
- Planning the sequence of construction and installation activities to allow subsequent testing and commissioning to proceed systematically
- Coordinating project stakeholders, suppliers, technical teams, and site personnel throughout an extended execution period
- Ensuring that installation activities remained aligned with the applicable design and project requirements
- Managing testing and verification requirements before progressing to final commissioning
Solution
MSI adopted a structured execution and coordination approach to address the technical and implementation requirements of the project:
- Design activities were coordinated with the project requirements to establish the technical basis for plant supply and site execution
- Procurement and supply activities were aligned with the requirements and sequence of the augmentation works
- Construction and installation activities were planned in a systematic sequence to maintain coordination between different stages of implementation
- Technical interfaces between design, plant supply, construction, and installation were managed throughout project execution
- Testing activities were incorporated into the execution process to verify the installed plant and associated works before commissioning
- Commissioning activities were coordinated as the final stage of the integrated project scope to support operational readiness of the completed augmentation works
- Coordination among the relevant project stakeholders was maintained across the design, supply, construction/installation, testing, and commissioning stages
Impact
The New Khimti Substation Augmentation project supports the implementation of planned power infrastructure works for Nepal Electricity Authority through an integrated approach to design, plant supply, construction/installation, testing, and commissioning.
- Supports the augmentation of the New Khimti Substation through coordinated project execution
- Establishes continuity between design, procurement, construction, installation, testing, and commissioning activities
- Supports systematic verification of installed plant and associated works before commissioning
- Contributes to the operational readiness of the augmentation works following completion of testing and commissioning
- Strengthens the implementation of power infrastructure through coordinated engineering and site execution
Conclusion
The New Khimti Substation Augmentation project represents an integrated power infrastructure assignment on Procurement of Plant for New Khimti Substation Augmentation (Design, Supply, Construction/Installation, Testing and Commissioning) covering design, plant supply, construction/installation, testing, and commissioning for Nepal Electricity Authority (NEA), Khimti Substation. The project requires coordinated execution across multiple technical stages, from initial design activities through site implementation and final commissioning.
MSI's involvement reflects its capability to coordinate technically interconnected activities within a structured power infrastructure project. By integrating design, procurement, construction/installation, testing, and commissioning within the defined project scope, MSI supports the systematic implementation and operational readiness of the New Khimti Substation Augmentation works.