Shallow Bases at Warehouse

Procurement and Supply of Aeronautical Ground Lighting (AGL) System

Procurement of Aeronautical Ground Lighting (AGL) System (Ref: MSI-PRJ-75-0358B) was implemented at Gautam Buddha International Airport (GBIA), Bhairahawa, Nepal, between Nov 2019 and Jan 2022. Executed by Northwest Civil Aviation Airport Construction Group Ltd., China, with Mahavir Shree International Pvt. Ltd. as sub-contractor, it comprised the supply of critical AGL materials, supporting enhanced airfield safety, efficiency, and compliance with international aviation standards.

ClientCivil Aviation Authority of Nepal (CAAN)
LocationGautam Buddha International Airport, Bharrahawa
CompletedJan 2022
DurationApproximately 2 Years and 2 months

Project Overview

Enhancing Aviation Infrastructure in Nepal: Mahavir Shree International’s Contribution to Gautam Buddha International Airport

Mahavir Shree International Pvt. Ltd. (MSIPL) is proud to have played a pivotal role in the successful completion of the Gautam Buddha International Airport (GBIA) Upgrading Component ICB-01 Project, located in Bhairahawa, Rupandehi, Nepal. This strategic infrastructure initiative, led by the Gautam Buddha International Airport and executed by Northwest Civil Aviation Airport Construction Group Ltd. (China), aimed to modernize and expand both airside and landside facilities at GBIA.

The project commenced in November 2019 and reached full completion in January 2022, marking a significant milestone in Nepal’s aviation development

PROJECT SCOPE:

Material Purchase Contract of Aeronautical Ground Light (AGL)

Project Name: The Material Purchase Contract of Aeronautical Ground Light (AGL)
Project Reference: MSI-PRJ-75-0358B
Location: Gautam Buddha International Airport (GBIA), Bhairahawa, Rupandehi, Nepal
Project Start Date: Nov 2019
Project Completion Date: Jan 2022
Client: Gautam Buddha International Airport
Main Contractor: Northwest Civil Aviation Airport Construction Group Ltd., China
Sub-Contractor: Mahavir Shree International Pvt. Ltd., Sinamangal, Kathmandu, Nepal

Under this contract, MSI was entrusted with the procurement, supply, and installation of critical components that support airport operations and passenger experience.

Key Works Completed Under the GBIA Upgrading Project

The broader project encompassed a wide range of infrastructure enhancements, including:

Installation of the Baggage Handling System (BHS) for international terminals

Procurement and supply of Aeronautical Ground Lights (AGL)

Supply of Weber rubber materials

Delivery of GRP poles for PALS-28 and SALS-10, along with necessary accessories

Installation of CCR/ASO equipment

Implementation of wayfinding signage for the International Terminal Building

Completion of Phase I and II of the AGL system

Installation of Airport Lighting Control and Monitoring System (ALCMS) and floodlight control panels

Execution of supplementary AGL agreements and accessories

Construction of elevators within the terminal infrastructure

All components were finalized and commissioned by January 2022, ensuring operational readiness and compliance with international standards.


MSIPL's Specialized Contributions

Mahavir Shree International Pvt. Ltd. delivered a comprehensive suite of services and equipment tailored to GBIA’s operational needs:

1. Baggage Handling System (BHS)

Design, manufacture, supply, installation, testing, and commissioning of:

International Departure BHS conveyor equipment

Rolling shutter security doors with draught curtains

Flat overlapping slat-type make-up carousels with friction drive

Control systems, steel supports, accessories, and protective guardrails

2. Arrival Reclaim Carousels

Design and installation of flat overlapping slat-type reclaim carousels with friction drive and rolling shutters for the International Arrival area

3. Logistics and Support

Supply of essential tools and spare parts

Factory inspections to ensure quality assurance

• Employee training programs to support operational handover and long-term maintenance


Project Completion and Impact

The successful delivery of this project has significantly enhanced GBIA’s capacity to manage international air traffic, streamline passenger movement, and improve safety and visibility through advanced lighting systems. MSIPL’s contributions reflect its commitment to precision, reliability, and collaborative execution in high-impact infrastructure projects.


Project Highlights

Collection of Shallow Bases

Collection of Shallow Bases

Equipments and Tools required for AGL

Equipments and Tools required for AGL

Shallow Bases at Warehouse

Shallow Bases at Warehouse